As discussed this morning we wish to affirm what we agreed as follows:
1- Septic tank in the island shall be emptied tomorrow morning or on the first day sailing is permitted. Also we strongly request that septic tanks and waste from contractor responsibility areas in the island must be removed periodically before reaching to overfill .
2- Company requires 7 PC’s stations or Lap tops for its personnel use for both islands . Internet facilities through main connection or individual modems is also required for our personnel.
3- Contractor is required to close the rest of the points raised by company Facility inspections -copies attached- and request a date not later than the end of next week for the verification inspection by company.
As for the unavailability of piping materials to be installed on AI North company cannot accept the reasons provided which are related to subcontractors not completing the production of the required spools .
As reported by Contractor there are 53 TIG welders on the islands which in our opinion are enough to open another work front in Zirku to fabricate painted raw material -straight run pipes and fittings - received from onshore and intended for the AI’s.. Please review your options in order to mitigate the already lost time and keeping in mind the criticality of PTW’s in the drilling areas and the bad weather which may cause more lost time.